Project Description:
WILLIAMSTOWN- RETAINING WALL REPLACEMENT & RELATED WORK ON ROUTE 2
The proposed project consists of replacing of a deteriorated concrete retaining wall on Route 2 in Williamstown. The project extends approximately 430 feet along Route 2 and is located about 1/3 of a mile west of its intersection with Route 7. A “vegetated prefabricated concrete bin-retaining wall” system is being proposed. A new paved swale and drainage structure will be constructed along the front of the new retaining wall and the existing pavement within the project limits will be replaced.
Location:
  • Town of Williamstown
  • Resident Engineer: Michael Wall
    Construction Contract Value: $1,899,977.00
    Construction Bid Price: $1,636,548.00
    Initial Construction Estimate: $2,200,917.25
    District: District 1

    Contracts (1) Progress
    # 67220 -- Construction Contract
    Retaining Wall Replacement and Related Work along a Section of Route 2 (Teconic Trail). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/08/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/10/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 08/28/2010
    Project Management
    100% Design 100% Package Received 05/10/2010
    100% Design 100% Package Comments to DE 06/15/2010
    100% Design 100% Plans Approved 06/15/2010
    25% Design 25% Package Received 09/21/2009
    25% Design 25% Package Comments to DE 10/02/2009
    25% Design 25% Package Approved 10/05/2009
    25% Design Design Public Hearing 11/17/2009
    25% Design 25% Plans Complete 10/13/2009
    75% Design 75% Package Received 03/10/2010
    75% Design 75% Plans Approved 04/22/2010
    Final Design PS&E Received 07/01/2010
    Final Design PS&E to FAPRO 08/04/2010