Project Description: |
ROCKLAND- BRIDGE REHABILITATION, BR# R-08-004, ROUTE 3 NB and SB OVER ROUTE 228 (HINGHAM STREET)
The proposed rehabilitation will include the replacement of the existing concrete deck and the pavement at the approaches. The existing steel beams will be sandblasted and painted. A temporary roadway will be constructed on the median to maintain traffic during construction.
|
Location: |
|
Resident Engineer: | Kevin Morrissey |
Construction Contract Value: | $6,998,775.53 |
Construction Bid Price: | $5,557,686.60 |
Initial Construction Estimate: | $3,870,643.75 |
District: | District 5 |
|
Bridges
|
|
|
|
|