Project Description:
METHUEN- BRIDGE CONSTRUCTION, BR# M-17-039, RIVERWALK OVER THE SPICKET FALLS DAM (PHASE 1)
This project consists of installing a pre-fabricated steel pedestrian bridge over the Spicket Falls Dam, near Hampshire, Lowell and Osgood Streets. The work will also include pavement construction, minor drainage improvements, retaining wall construction, metal pipe rail installation, concrete pavers, pavement markings, landscaping and other incidental work.
Location:
  • Town of Methuen
  • Resident Engineer: Albert Kwok
    Construction Contract Value: $1,479,803.00
    Construction Bid Price: $1,341,458.00
    Initial Construction Estimate: $666,182.00
    District: District 4
    Current Status: This project is completed. Only punch list work remains. (as of 02/11/2008)
    Additional Info: Final inspection was completed on 11/16/07. Bridge section will perform his inspection shortly. (as of 02/11/2008)

    Contracts (1) Progress
    # 42760 -- Construction Contract
    Methuen - Riverwalk over the Spicket Falls Dam M-17-039 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/21/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is completed. Only punch list work remains.
    Additional Info
    Final inspection was completed on 11/16/07. Bridge section will perform his inspection shortly.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/31/1999
    Project Review Committee PRC Approved 09/27/1999
    Project Status Advertised 09/22/2001
    Project Status Advertised 12/04/2004
    Project Status Advertised 05/14/2005
    Project Management
    100% Design 100% Package Received 10/27/2004
    100% Design 100% Package Comments to DE 11/20/2001
    25% Design 25% Package Received 02/18/2000
    25% Design 25% Package Comments to DE 11/30/2000
    75% Design 75% Package Received 03/15/2001
    75% Design 75% Package Comments to DE 05/24/2001
    Final Design PS&E Received 07/29/2004
    Final Design PS&E Received 05/09/2005
    Final Design PS&E to FAPRO 05/10/2005