DISTRICT 5- DRAINAGE IMPROVEMENTS AT VARIOUS LOCATIONS IN AREA B (3 SEPARATE CONTRACTS)
Location:
Resident Engineer: Stephen Soares
Construction Contract Value: $990,129.16
Construction Bid Price: $615,130.00
Initial Construction Estimate: $452,400.00
District: District 5

Contracts (1) Progress
# 32295 -- Construction Contract
Drainage Improvements at Various Locations. (Area B) - (3 Separate Contracts) Re-Advertised. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/01/2002
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/30/1999
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 09/01/2001
    Project Status Advertised 03/02/2002