Project Description:
NORTHAMPTON- ROUNDABOUT CONSTRUCTION AT NORTH MAIN STREET, BRIDGE ROAD AND LOOK MEMORIAL PARK ENTRANCE
This project will enhance safety and improve the efficiency of the traffic flow at the intersection of North Main Street (Route 9), Bridge Road and Look Memorial Park. The work will include major geometric improvements, replacing the two existing offset T intersections with a roundabout. All four approaches will be realigned to into a four-legged roundabout, featuring a planted island and an attractive sign for Look Memorial Park.
Location:
  • City of Northampton
  • Resident Engineer: Joseph Burek
    Construction Contract Value: $1,893,284.00
    Construction Bid Price: $1,645,622.00
    Initial Construction Estimate: $2,097,589.25
    District: District 2

    Contracts (1) Progress
    # 61465 -- Construction Contract
    Roundabout Installation and Related Work on Route 9 (North Main Street) at Bridge Street and Look Memorial Park. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/24/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 06/20/2001
    Project Status Advertised 08/29/2009
    Project Management
    100% Design 100% Package Received 04/01/2009
    100% Design 100% Package Received 07/31/2009
    100% Design 100% Package Comments to DE 05/15/2009
    100% Design 100% Package Comments to DE 08/14/2009
    25% Design 25% Package Received 03/02/2005
    25% Design 25% Package Comments to DE 05/23/2005
    25% Design Design Public Hearing 06/06/2007
    75% Design 75% Package Received 01/25/2008
    75% Design 75% Package Received 12/18/2008
    75% Design 75% Package Comments to DE 02/27/2009
    75% Design 75% Package Rejected 06/23/2008
    Final Design PS&E Received 08/24/2009
    Final Design PS&E to FAPRO 08/25/2009