NEWBURY- BRIDGE REPLACEMENT, N-10-010, ROUTE 1A (HIGH ROAD) OVER THE PARKER RIVER
The proposed project will replace the existing bridge in its present location with improvements to the approach roadway. The original design entailed providing one lane of traffic in each direction and a sidewalk during the construction. Based on additional deterioration discovered when the project first commenced, the design was modified to utilize single stage construction with the bridge being closed and all traffic detoured. The formal, signed detour route utilizes Route 133, Route 1 and Hanover Street.
Location:
  • Town of Newbury
  • Resident Engineer: David Conroy
    Construction Contract Value: $14,125,670.00
    Construction Bid Price: $12,742,418.00
    Initial Construction Estimate: $8,576,635.00
    District: District 4

    Contracts (2) Progress
    # 30142 -- Design -- Bridge Rehab/Recon/New Const
    Newbury - Route 1A (High Road) over Parker River BR#N-10-010. Preliminary/ Final Design. Final
    # 49211 -- Construction Contract
    Newbury - Bridge Replacement (N-10-010) (Concrete) - Route 1 A (High Road) over the Parker River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/17/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 09/10/2005
    Project Status Advertised 11/26/2005
    Project Status Advertised 09/09/2006
    Project Management
    100% Design 100% Package Received 09/12/2002
    100% Design 100% Package Comments to DE 03/28/2003
    100% Design 100% Plans Complete 06/18/2003
    25% Design 25% Package Received 04/27/2001
    25% Design 25% Package Comments to DE 05/19/2001
    25% Design Design Public Hearing 11/15/2001
    75% Design 75% Package Received 11/16/2001
    75% Design 75% Package Comments to DE 03/12/2002
    Final Design PS&E Received 04/11/2005
    Final Design PS&E to FAPRO 05/12/2005