Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CONCORD- LINCOLN- BRIDGE REPLACEMENT, BR# C-19-005 = L-12-003 ROUTE 117 OVER SUDBURY RIVER (LEE'S BRIDGE)
The work consists of replacing the existing bridge structure carrying Route 117 over the Sudbury River and includes the construction and subsequent removal of a temporary roadway and bridge.
Location:
  • Town of Concord
  • Town of Lincoln
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $7,938,382.63
    Estimated Total Federal Participating Construction Cost: $2,000,000.00
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 08/10/2002 )

    Contracts (4) Progress
    # 30145 -- Design -- Bridge Rehab/Recon/New Const
    Concord - Route 117 over Sudbury River, BR#C-19-005. Preliminary and Final Design. Final
    # 33126 -- Construction Contract
    Bridge Replacement C-19-005=L-12-003 (Concrete) Route 117 over Sudbury River.
    # 33289 -- Design -- Bridge Open End
    Statewide-Engineering services for bridge rehab & emergency services Final
    # 98013 -- Design -- Bridge Open End
    Off System Round 5 Bridge R&R Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 09/29/2001
    Project Status Advertised 08/10/2002
    Project Management