Project Description:
MONTAGUE- BRIDGE REPLACEMENT, M-28-028, PROSPECT STREET OVER SPRING STREET
The purpose of this project is to replace the Prospect Street bridge over Spring Street. The new bridge will be a single concrete span on concrete abutments. The curb to curb width will be 23 feet with a 6 foot sidewalk. The bridge will be closed during construction.
Location:
  • Town of Montague
  • Resident Engineer: Sean Burke
    Construction Contract Value: $2,468,674.00
    Construction Bid Price: $2,213,004.00
    Initial Construction Estimate: $2,676,658.00
    District: District 2

    Contracts (3) Progress
    # 32184 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract Q Final
    # 58223 -- Construction Contract
    Bridge Replacement (M-28-028) (Concrete) - Prospect Street over Spring Street Completed
    # 64318 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/08/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 10/04/2007
    Project Status Advertised 02/14/2009
    Project Management
    100% Design 100% Package Received 07/24/2008
    100% Design 100% Package Comments to DE 08/22/2008
    25% Design 25% Package Received 12/22/2003
    25% Design 25% Package Comments to DE 04/20/2004
    25% Design Design Public Hearing 02/15/2005
    75% Design 75% Package Received 07/18/2005
    75% Design 75% Package Comments to DE 11/10/2005
    Final Design PS&E Received 10/31/2008
    Final Design PS&E to FAPRO 02/11/2009
    Consultant Contract Process Scope to DE 07/15/2002
    Consultant Contract Process NTP Issued 08/23/2002