| Project Description: |
STERLING- BRIDGE REPLACEMENT, S-25-008, MUDDY POND ROAD OVER THE STILLWATER RIVER
This town-owned, structurally deficient will be replaced with a new bridge that will be six feet wider with a sidewalk along one side. The new bridge will consist of a single span constructed upon the existing bridge abutments. The bridge will be closed for construction and traffic detoured.
|
| Location: |
|
| Resident Engineer: | Lisa Spezzaferro-Pelleti![]() |
| Construction Contract Value: | $1,215,140.00 |
| Construction Bid Price: | $1,049,037.00 |
| Initial Construction Estimate: | $808,829.30 |
| District: | District 3 |
| Current Status: | MassHighway moved this work to a new contractor. Work on this project has resumed. (as of 07/20/2007) |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||