Project Description:
LYNNFIELD- INSTALLATION OF A ROADWAY LIGHTING SYSTEM AT GOODWIN CIRCLE
The project consists of the placement of roadway lighting and controls. The project will include the installation of approximately 14 Street Lights located approximately 5 feet from the edge of roadway. All trenching and conduit will be located as close to the roadway as possible.
Location:
  • Town of Lynnfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Ranjit Sivasubramaniam
    Estimated Total Contract Cost: $278,981.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 02/11/2006 )

    Contracts (1) Progress
    # 33058 -- Design -- Traffic Open End
    Statewide - provide traffic engineering services in connection with traffic signal improvement projects at State Highway Locations. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/23/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 11/10/2005
    Project Status Advertised 02/11/2006
    Project Management
    100% Design 100% Package Received 06/28/2007
    25% Design 25% Package Received 04/16/2004
    25% Design 25% Package Approved 09/23/2004
    25% Design Design Public Hearing 11/29/2005
    75% Design 75% Package Received 02/03/2005
    75% Design 75% Plans Approved 04/26/2005
    Final Design PS&E Received 01/13/2006
    Final Design PS&E to FAPRO 01/30/2006