WEYMOUTH- SIGNALIZATION & IMPROVEMENTS ON ROUTE 18 (3 LOCATIONS) @ WEST STREET; @ PARK AVENUE; @ COLUMBIAN STREET
This project makes safety improvements at three congested signalized intersections by upgrading traffic control signals and adding exclusive turning lanes.
Location:
  • Town of Weymouth
  • Resident Engineer: Phuong Tran
    Construction Contract Value: $11,285,626.00
    Construction Bid Price: $9,983,819.00
    Initial Construction Estimate: $5,859,742.50
    District: District 4

    Contracts (2) Progress
    # 30202 -- Design -- Traffic Signing/Signals
    Statewide - Traffic engineering services with traffic signal improvement projects. Final
    # 48771 -- Construction Contract
    Weymouth - Rte 18 (Main St.) @ Park Ave, West & Columbian Sts. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/25/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/17/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 05/23/2002
    Project Status Advertised 07/08/2006
    Project Management
    100% Design 100% Package Received 09/23/2004
    100% Design 100% Package Comments to DE 01/12/2005
    25% Design 25% Package Received 10/02/2001
    25% Design 25% Package Comments to DE 02/08/2002
    25% Design Design Public Hearing 07/11/2002
    75% Design 75% Package Received 11/06/2002
    75% Design 75% Package Comments to DE 06/30/2004
    Final Design PS&E Received 07/20/2005
    Final Design PS&E to FAPRO 06/30/2006
    Consultant Contract Process Workhours Approved 11/27/2000