Project Description: |
BUCKLAND- BRIDGE REPLACEMENT, BR# B-28-012 HOG HOLLOW ROAD OVER CLESSON BROOK
The proposed project consists of constructing a precast/prestressed concrete box beam superstructure on modified existing concrete abutments with improvements to the approach roadway. The proposed work also includes construction of a temporary pedestrian bridge.
|
Location: |
|
Resident Engineer: | Paul Phelps |
Construction Contract Value: | $468,808.00 |
Construction Bid Price: | $398,917.00 |
Initial Construction Estimate: | $319,250.00 |
District: | District 1 |
Current Status: | Project complete (as of 09/23/2004) |
|