Project Description:
BUCKLAND- BRIDGE REPLACEMENT, BR# B-28-012 HOG HOLLOW ROAD OVER CLESSON BROOK
The proposed project consists of constructing a precast/prestressed concrete box beam superstructure on modified existing concrete abutments with improvements to the approach roadway. The proposed work also includes construction of a temporary pedestrian bridge.
Location:
  • Town of Buckland
  • Resident Engineer: Paul Phelps
    Construction Contract Value: $468,808.00
    Construction Bid Price: $398,917.00
    Initial Construction Estimate: $319,250.00
    District: District 1
    Current Status: Project complete (as of 09/23/2004)

    Contracts (1) Progress
    # 33214 -- Construction Contract
    Bridge Replacement B-28-012 (Concrete) - Hog Hollow Road over Clesson Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/01/2003
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/20/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 08/24/2002