Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW ASHFORD- EMERGENCY LEDGE REMOVAL AND RELATED WORK ALONG ROUTE 7
Location:
  • Town of New Ashford
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Albert Li
    Estimated Total Federal Participating Construction Cost: $150,000.00
    District: District 1
    Current Status: This project has been advertised for construction bids. (as of 02/23/2002 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/12/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 02/23/2002
    Project Management