Project Description:
AMESBURY- BRIDGE REPLACEMENT, A-07-010, MAIN STREET OVER MERRIMACK RIVER (1ST LT. DEREK S. HINES MEMORIAL BRIDGE) (DESIGN-BUILD)
The proposed work consists of a superstructure and substructure replacement, with a possible rehabilitation of the North abutment and incidental improvements to the approaching roadways.
Location:
  • Town of Amesbury
  • Resident Engineer: Ryan Wilcox
    Construction Contract Value: $33,981,041.75
    Construction Bid Price: $30,700,000.00
    Initial Construction Estimate: $33,925,263.00
    District: District 4

    Contracts (6) Progress
    # 30237 -- Design -- Bridge Rehab/Recon/New Const
    Amesbury - Main Street over the Merrimac River. BR# A-07-010 Final
    # 49402 -- Design -- Hwy Eng Open End
    Work will generally consist of providing design and engineering services to the Projects Division on an open end basis for various statewide Value Engineering Studies. Final
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 61787 -- Construction Contract
    Bridge Replacement (A-07-010) (Steel) - Main Street over the Merrimack River (1st Lt. Derel S. Hines Memorial Bridge). (DESIGN / BUILD Project) Completed
    # 62938 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering for various projects .

    Bridges

    Contract Dates
    Notice to Proceed: 03/16/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    Preliminary Design
    FS&T prepared the design up to sketch plans and and 75% hwy Plans. This is now DB project; NTP was issued on 3/16/10 to DB Team (Barletta/VHB); VHB & Subcons are the designer
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/10/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee Letter 06/01/2000
    Project Status Advertised 09/19/2009
    Project Management
    25% Design 25% Package Received 12/13/2004
    25% Design 25% Package Comments to DE 03/07/2005
    25% Design Design Public Hearing 04/26/2005
    25% Design Design Public Hearing 10/01/2008
    75% Design 75% Package Received 01/12/2009
    Final Design PS&E Received 09/10/2009
    Final Design PS&E to FAPRO 09/16/2009
    Consultant Contract Process Scope to DE 03/02/2001
    Consultant Contract Process NTP Issued 11/20/2001