Project Description:
SHREWSBURY- SIGNALIZATION & IMPROVEMENTS ON ROUTE 9 (TURNPIKE RD) FROM QUINSIGAMOND AVENUE TO MAPLE AVENUE (STREETSCAPE TRANSPORTATION ENHANCEMENT)
This project is being undertaken as mitigation for the development of a Walgreens store at this location. The proposed work includes intersection realignment and minor widening along with the installation of new signal equipment, signs and pavement markings.
Location:
  • Town of Shrewsbury
  • Resident Engineer: Thomas Donnelly
    Construction Contract Value: $5,653,769.00
    Construction Bid Price: $5,222,924.10
    Initial Construction Estimate: $5,771,434.50
    District: District 3

    Contracts (1) Progress
    # 51511 -- Construction Contract
    Shrewsbury- Roadway Reconstruction Rte. 9 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/17/2007
    Contract Information
    Project Designer: Other
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/14/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Review Committee Resubmitted 11/30/2005
    Project Status Advertised 09/23/2006
    Project Management
    25% Design 25% Package Received 09/26/2005
    25% Design 25% Package Comments to DE 12/02/2005
    25% Design Design Public Hearing 03/09/2006
    75% Design 75% Package Received 06/20/2006
    Final Design PS&E to FAPRO 09/18/2006