| Project Description: |
SHREWSBURY- SIGNALIZATION & IMPROVEMENTS ON ROUTE 9 (TURNPIKE RD) FROM QUINSIGAMOND AVENUE TO MAPLE AVENUE (STREETSCAPE TRANSPORTATION ENHANCEMENT)
This project is being undertaken as mitigation for the development of a Walgreens store at this location. The proposed work includes intersection realignment and minor widening along with the installation of new signal equipment, signs and pavement markings.
|
| Location: |
|
| Resident Engineer: | Thomas Donnelly![]() |
| Construction Contract Value: | $5,653,769.00 |
| Construction Bid Price: | $5,222,924.10 |
| Initial Construction Estimate: | $5,771,434.50 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||