Project Description:
AUBURN- RESURFACING & RELATED WORK ON MILLBURY STREET, FROM CENTRAL STREET TO ROUTE 20 (WASHINGTON STREET)
This project involves roadway reclamation and resurfacing, drainage improvements, installation of granite curb, sidewalk construction, and pavement marking and sign installation. The project extends from Central Street to Route 20, a distance of 0.71 miles.
Location:
  • Town of Auburn
  • Resident Engineer: Neil Raymond
    Construction Contract Value: $897,442.00
    Construction Bid Price: $782,956.90
    Initial Construction Estimate: $996,167.00
    District: District 3

    Contracts (1) Progress
    # 65950 -- Construction Contract
    Resurfacing and Related Work on a Section of Millbury Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/21/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/18/2000
    Project Review Committee PRC Approved 04/24/2000
    Project Status Advertised 07/10/2010
    Project Management
    100% Design 100% Package Received 03/19/2010
    100% Design 100% Package Comments to DE 03/26/2010
    Final Design PS&E Received 05/25/2010
    Final Design PS&E to FAPRO 07/07/2010