| Project Description: |
DISTRICT 4- (NORFOLK & SUFFOLK COUNTIES) SCHEDULED AND EMERGENCY REPAIRS TO ABUTMENTS, PIERS AND COLUMNS (2 SEPARATE CONTRACTS)
This work consists of removing deteriorated concrete from stem piers, pier caps, pier columns, walls and abutments and replacing excavated concrete.
|
| Location: | |
| Resident Engineer: | Robert Huettner![]() |
| Construction Contract Value: | $2,247,613.25 |
| Construction Bid Price: | $2,189,578.25 |
| Initial Construction Estimate: | $2,160,000.00 |
| District: | District 4 |
| Current Status: | Work under this current contract consists of removing deteriorated concrete from stem piers, pier caps , pier columns , walls and abutments and replacing excavated concrete and damaged reinforcing steel. (as of 08/31/2005) |
| Additional Info: | This contract is complete and is in the process of being finaled. (as of 08/31/2005) |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||