Project Description: |
DISTRICT 5- RESURFACING AND RELATED WORK AT VARIOUS LOCATIONS IN AREA B
The work under this contract consists of cold planing and resurfacing various areas in Dartmouth, New Bedford and Seekonk. Work includes adjustment and rebuilding of existing drainage and sanitary structures, the adjustment of gate boxes, repairing frost heaves, replacement of existing traffic signal loop detectors and the application of pavement markings.
|
Location: | |
Resident Engineer: | -- not assigned -- |
Construction Contract Value: | $2,226,616.56 |
Construction Bid Price: | $1,184,000.00 |
Initial Construction Estimate: | $1,145,245.00 |
District: | District 5 |
|
Bridges |
|
|
|
|