Project Description:
RANDOLPH- BRIDGE REPLACEMENT, R-01-012, MDC ACCESS ROAD OVER ROUTE 24 (NB & SB)
This project consists of the replacement of the former MDC (now DCR) Access Bridge over Route 24. This bridge is commonly referred to as the "Horse Bridge". The new bridge will be a pre-engineered "Channel Bridge". The project includes minor work to the approaches.
Location:
  • Town of Randolph
  • Resident Engineer: Anthony Neve
    Construction Contract Value: $4,631,355.50
    Construction Bid Price: $3,858,630.00
    Initial Construction Estimate: $4,070,075.00
    District: District 4

    Contracts (2) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57641 -- Construction Contract
    Bridge Replacement (R01-012) (Concrete) - DCR Access Road over Route 24 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/10/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 06/26/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Status Advertised 09/30/2005
    Project Status Advertised 11/08/2008
    Project Management
    100% Design 100% Package Received 09/18/2008
    100% Design 100% Package Comments to DE 09/12/2005
    25% Design 25% Package Received 05/10/2004
    25% Design 25% Package Comments to DE 10/27/2004
    25% Design 25% Package Approved 08/19/2004
    25% Design Design Public Hearing 02/08/2005
    75% Design 75% Package Received 05/23/2005
    75% Design 75% Package Comments to DE 07/15/2005
    Final Design PS&E Received 10/30/2008
    Final Design PS&E to FAPRO 11/04/2008
    Consultant Contract Process Scope to DE 09/03/2003
    Consultant Contract Process NTP Issued 11/26/2003
    Consultant Contract Process Workhours Approved 11/17/2003