NEWBURY- BRIDGE REPLACEMENT, BR# N-10-005, HAY STREET OVER THE LITTLE RIVER
This project consists of replacing the structurally deficient Hay Street Bridge over the Little River with a new bridge. The existing bridge and piers will be removed and replaced with a new single span bridge with new bridge abutments constructed behind the existing abutments. The new bridge will be 28 feet wide from curb to curb. The bridge roadway approaches will be reconstructed. No sidewalk is being proposed for the bridge or roadway approaches. The bridge will be closed during construction and traffic detoured.
Location:
  • Town of Newbury
  • Resident Engineer: David Conroy
    Construction Contract Value: $1,181,721.00
    Construction Bid Price: $1,024,474.00
    Initial Construction Estimate: $917,068.30
    District: District 4
    Current Status: This poject is complete. (as of 02/15/2008)

    Contracts (1) Progress
    # 43701 -- Construction Contract
    Newbury - Bridge Replacement (N-10-005) Hay Street over the Little River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/21/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This poject is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/05/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Status Advertised 08/27/2005
    Project Management
    100% Design 100% Package Received 07/01/2005
    100% Design 100% Package Comments to DE 08/08/2005
    100% Design 100% Plans Complete 08/11/2005
    25% Design 25% Package Received 02/27/2002
    25% Design 25% Package Comments to DE 06/04/2004
    25% Design Design Public Hearing 11/21/2002
    75% Design 75% Package Received 09/28/2004
    75% Design 75% Package Comments to DE 02/18/2005
    Final Design PS&E Received 08/22/2005
    Final Design PS&E to FAPRO 08/22/2005