Project Description: |
TAUNTON- SUPERSTRUCTURE REPLACEMENT, T-01-051, HOLLOWAY STREET OVER ROUTE 140 (NB) INCLUDES RAILING & CURB RETROFITTING ON T-01-057
The purpose of this project is to replace the superstructure of the bridge carrying Holloway Street over Route 140 NB with a three span continuous superstructure. The railings and curbs of bridge carrying Holloway Street over Route 140 SB will also be replaced.
|
Location: |
|
Resident Engineer: | Michael Giovanelli |
Construction Contract Value: | $2,671,041.00 |
Construction Bid Price: | $2,294,819.00 |
Initial Construction Estimate: | $2,340,964.35 |
District: | District 5 |
|
Bridges
|
|
|
|
|