Project Description: |
FALL RIVER- SOMERSET- SWANSEA- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-195
This project will resurface various sections of I-195 including ramps and some bridge approaches located in Fall River, Somerset and Swansea. Additional work (as needed) includes various drainage work, edging/curb replacement or resetting, application of temporary and permanent pavement markings, and other related work incidental to a project of this nature.
|
Location: |
|
Design Responsibility: | In-House Boston |
Right of Way Responsibility: | MassDOT |
Project Manager: | Brian Haggerty |
Estimated Total Federal Participating Construction Cost: | $1,140,000.00 |
District: | District 5 |
Current Status: | This project has been advertised for construction bids. (as of 05/12/2001 ) |
|
Bridges |
|
|
|