Project Description:
PITTSFIELD- BRIDGE REPLACEMENT, P-10-049, LAKEWAY DRIVE OVER ONOTA LAKE
This bridge replacement project carries Lakeway Drive over Onota Lake. Work also includes reconstruction of bridge approaches, sidewalk, highway guardrail, pavement marking, loam borrow and seeding, and other incidental work. Only one lane will remain open for bi-directional vehicular traffic with a sign “YIELD TO ONCOMING TRAFFIC”, and other construction warning signs during construction.
Location:
  • City of Pittsfield
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Peter Lamarre
    Construction Bid Price: $2,688,888.88
    District: District 1

    Contracts (3) Progress
    # 108805 -- Construction Contract
    Bridge Replacement Br. No. P-10-049 (NEXT Beams) Lakeway Drive over Onota Lake Completed
    # 59588 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/23/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/18/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 07/13/2019
    Project Management
    100% Design 100% Package Received 11/30/2018
    25% Design 25% Package Received 01/31/2002
    25% Design 25% Package Received 03/16/2012
    25% Design 25% Package Comments to DE 04/02/2012
    25% Design 25% Package Received - Resub 1 06/23/2017
    25% Design Design Public Hearing 05/23/2002
    75% Design 75% Package Received 02/17/2004
    75% Design 75% Package Comments to DE 04/22/2004
    75% Design 75% Package Received - Resub 1 07/19/2018
    Final Design PS&E Received 03/08/2019
    Final Design PS&E to FAPRO 07/11/2019
    Consultant Contract Process Scope to DE 11/01/2000
    Consultant Contract Process NTP Issued 12/15/2016