Project Description: |
ATHOL- ERVING- GILL- GREENFIELD- ORANGE- PHILLIPSTON- WENDELL- SAFETY IMPROVEMENTS ALONG ROUTE 2
|
Location: |
|
Resident Engineer: | Michael Lonergan |
Construction Contract Value: | $233,915.00 |
Construction Bid Price: | $358,315.00 |
Initial Construction Estimate: | $367,000.00 |
District: | District 2 |
Current Status: | Physical work completed. (as of 08/19/2005) |
|