Project Description: |
WILLIAMSTOWN- RETAINING WALL INSTALLATION, LOCATED AT THE INTERSECTION OF SCOTT HILL AND ROUTE 43
|
Location: |
|
Resident Engineer: | Russell Duval |
Construction Contract Value: | $419,763.90 |
Construction Bid Price: | $369,562.50 |
Initial Construction Estimate: | $368,790.00 |
District: | District 1 |
Current Status: | Project is complete. (as of 06/21/2005) |
|
Bridges |
|
|
|
|