Project Description:
BELCHERTOWN- BRIDGE BETTERMENT, BR# B-05-007, MILL VALLEY ROAD (ROUTE 181) OVER JABISH BROOK
This project involves replacing the structurally deficient Mill Valley Road Bridge where it crosses over Jabish Brook. A temporary bridge will be constructed adjacent to the existing bridge so access can be maintained while the new bridge is constructed.
Location:
  • Town of Belchertown
  • Resident Engineer: Jane Trudeau
    Construction Contract Value: $397,645.00
    Construction Bid Price: $348,545.00
    Initial Construction Estimate: $227,515.00
    District: District 2
    Current Status: Physical work completed (as of 09/11/2006)

    Contracts (2) Progress
    # 32178 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract K Final
    # 42548 -- Construction Contract
    Belchertown - Bridge Rehabilitation Bridge No. B-05-007 Route 181(Valley Mill Road) over Jabish Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Physical work completed
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/06/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 05/21/2005
    Project Management
    Final Design PS&E Received 05/18/2005
    Final Design PS&E to FAPRO 05/18/2005