Project Description:
WORCESTER- BRIDGE REHABILITATION, BR# W-44-082 ROUTE I-290 EB & WB OVER CSX R.R. AND VARIOUS CITY STREETS
Work on this project involves the replacement of the bridge deck on I-290 through the raised section of highway in downtown Worcester. The work area will begin at the I-290/Grafton Street ramps and continue easterly to a point just east of the Shrewsbury Street ramp. This structure crosses over several city streets, the commuter rail (CSX Railroad) and several parking lots. Work during the 2004 construction season comprises the full removal and replacement of the Eastbound deck. Work during the 2005 construction season comprises the same scope but on the westbound deck. Traffic on I-290 through the work area is restricted to two lanes in each direction. This will be the case during the deck replacements, but all lanes will open during the winter months.
Location:
  • City of Worcester
  • Resident Engineer: Kevin Troy
    Construction Contract Value: $17,998,363.14
    Construction Bid Price: $15,982,015.00
    Initial Construction Estimate: $16,489,146.00
    District: District 3
    Current Status: Barrier repairs have been completed. Patching of piers is completed. Painting of bridge steel is still ongoing. (as of 09/18/2006)

    Contracts (1) Progress
    # 34025 -- Construction Contract
    Bridge Rehabilitation W-44-082- Interstate 290 over CSX Railroad and 4 City Streets. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/12/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Barrier repairs have been completed. Patching of piers is completed. Painting of bridge steel is still ongoing.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/08/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 02/02/2002
    Project Status Advertised 06/28/2003
    Project Management