SHERBORN- BRIDGE REPLACEMENT, S-12-003, WHITNEY STREET OVER CSX R.R.
The proposed project consists of replacing the existing Whitney Street bridge over the CSX railroad in its present location with minor improvements to the approach roadways. The bridge will be constructed in stages, keeping one lane of traffic open at all times.
Location:
  • Town of Sherborn
  • Resident Engineer: Julio Fontecchio
    Construction Contract Value: $2,043,471.00
    Construction Bid Price: $1,695,774.03
    Initial Construction Estimate: $2,022,340.00
    District: District 3

    Contracts (1) Progress
    # 54045 -- Construction Contract
    Sherborn - Bridge Superstructure Replacement (S-12-003) Whitney Street over CSX Railroad Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/26/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/11/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 09/15/2007
    Project Management
    100% Design 100% Package Received 02/26/2007
    100% Design 100% Package Comments to DE 05/31/2007
    25% Design 25% Package Received 11/12/2004
    25% Design 25% Package Comments to DE 01/20/2006
    25% Design Design Public Hearing 03/21/2006
    25% Design 25% Plans Complete 02/01/2006
    75% Design 75% Package Received 09/15/2006
    Final Design PS&E Received 08/22/2007
    Final Design PS&E to FAPRO 09/11/2007
    Consultant Contract Process Scope to DE 04/10/2002
    Consultant Contract Process NTP Issued 04/28/2004
    Consultant Contract Process Workhours Approved 03/08/2004