Project Description:
SPRINGFIELD- BRIDGE PRESERVATION, S-24-068, LIBERTY STREET OVER ROUTE I-291 AND S-24-069, ARMORY STREET OVER ROUTE I-291
The proposed work consists of repairing the concrete bridge decks; replacing the sidewalks and safety walks; installing replacement lighting, new steel bridge rail and safety screening; minor widening of the approaches; full cleaning and painting of the structural steel beams on each bridge, and installing new asphalt pavement. Construction will be staged so that one lane of travel will be maintained at all times over each bridge.
Location:
  • City of Springfield
  • Resident Engineer: Joseph Borowiec
    Construction Contract Value: $5,234,611.50
    Construction Bid Price: $4,360,510.00
    Initial Construction Estimate: $3,725,000.00
    District: District 2

    Contracts (2) Progress
    # 36569 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 57676 -- Construction Contract
    2 Bridge Deck Rehabilitation Including Painting (S-24-68 & S-24-69) - Liberty and Armory Streets over Interstate 291. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/23/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/18/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 02/05/2001
    Project Status Advertised 09/23/2006
    Project Status Advertised 10/04/2008
    Project Management
    Final Design PS&E Received 09/08/2008
    Final Design PS&E to FAPRO 09/15/2008
    Consultant Contract Process Scope to DE 05/31/2005
    Consultant Contract Process NTP Issued 06/30/2005