Project Description:
WESTFIELD- RECONSTRUCTION OF ROUTE 20 (MAIN STREET) AND ROUTE 10/202 (BROAD STREET)
The purpose of this project is to improve vehicular and pedestrian safety and promote efficient traffic operation along Main Street, Broad Street, South Broad Street and Park Square.
Location:
  • City of Westfield
  • Resident Engineer: Sean Milligan
    Construction Contract Value: $12,500,132.00
    Construction Bid Price: $11,957,543.87
    Initial Construction Estimate: $14,393,653.00
    District: District 2

    Contracts (1) Progress
    # 62565 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Route 20 (Main Street) and Route 10/202 (Broad Street) (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/02/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 01/23/2010
    Project Management
    100% Design 100% Package Received 11/23/2009
    100% Design 100% Package Comments to DE 10/07/2009
    25% Design 25% Package Received 12/31/2002
    25% Design 25% Package Comments to DE 04/18/2003
    25% Design Design Public Hearing 09/30/2003
    75% Design 75% Package Received 08/23/2004
    75% Design 75% Package Comments to DE 12/15/2004
    Final Design PS&E Received 12/31/2009
    Final Design PS&E to FAPRO 01/15/2010