Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WESTMINSTER- BRIDGE REPLACEMENT, W-28-021, ROUTE 2 (EB & WB) OVER WEST MAIN STREET (ROUTE 140)
The proposed project involves the replacement of the Route 2 Bridge over West Main Street (Route 140). The proposed work will involve the demolition of the existing bridges (eastbound and westbound). The minimum vertical clearance will be increased in order to achieve the standard clearance. Both bridges will remain open to traffic throughout construction.
Location:
  • Town of Westminster
  • Resident Engineer: Carmen Ramirez
    Construction Contract Value: $13,671,253.00
    Construction Bid Price: $11,378,916.25
    Initial Construction Estimate: $14,065,277.00
    District: District 3

    Contracts (7) Progress
    # 30276 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54619 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection and design and analysis of complex foundation rehabilitation projects. Final
    # 57733 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 62371 -- Construction Contract
    Bridge Replacement (W-25-21) (Steel) Route 2 (EB & WB) over West Main Street (Route 140). (ABP) Completed
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/06/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/13/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 02/09/2001
    Project Status Advertised 09/26/2009
    Project Status Advertised 12/26/2009
    Project Management
    100% Design 100% Package Received 04/28/2009
    100% Design 100% Package Received 08/21/2009
    100% Design 100% Package Comments to DE 06/25/2009
    25% Design 25% Package Received 03/31/2003
    25% Design 25% Package Comments to DE 12/30/2003
    25% Design Design Public Hearing 06/30/2004
    75% Design 75% Package Received 09/11/2008
    75% Design 75% Package Comments to DE 01/30/2009
    Final Design PS&E Received 09/22/2009
    Final Design PS&E to FAPRO 09/23/2009
    Consultant Contract Process Scope to DE 06/12/2001
    Consultant Contract Process NTP Issued 01/08/2002