Project Description:
FITCHBURG- LEOMINSTER- IMPROVEMENTS & SIGNALIZATION OF ROUTE 12 (PHASE I & II)
Phase 1 improvements will include minor pavement widening along the Route 12 corridor to provide two 11.50-foot travel lanes and 8-foot shoulders. Intersection improvements at the junction of Route 12 and Bemis Road will include widening Route 12, realigning and widening Bemis Road, and the installation of new traffic signals. Phase 2 improvements will include minor pavement widening along the Route 12 corridor to provide two 11.50-foot travel lanes and 8-foot shoulders, adding auxiliary lanes on Route 12 at the Erdman Way intersection and upgrading the existing traffic signal at the intersection of Route 12 with Erdman Way. The proposed scope of work for both sections will also include new sidewalks and granite curbing on both sides of the roadway.
Location:
  • City of Fitchburg
  • City of Leominster
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $8,490,034.00
    Construction Bid Price: $7,511,031.00
    Initial Construction Estimate: $7,350,036.00
    District: District 3

    Contracts (4) Progress
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 51236 -- Construction Contract
    Leominster - Fitchburg - Roadway Reconstruction and Related Work on a Section of Route 12 (North & Water Streets) Completed
    # 54827 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57728 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/06/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/22/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 04/10/2003
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 05/24/2006
    100% Design 100% Package Comments to DE 08/08/2006
    25% Design 25% Package Received 10/01/2002
    25% Design 25% Package Comments to DE 02/27/2004
    75% Design 75% Package Received 04/21/2004
    75% Design 75% Package Comments to DE 04/22/2005
    Final Design PS&E to FAPRO 09/18/2006
    Consultant Contract Process Scope to DE 04/10/2001
    Consultant Contract Process NTP Issued 12/05/2001