| Project Description: |
HARVARD- SHIRLEY- BRIDGE REPLACEMENT, BR# H-09-025=S-13-018, HOSPITAL ROAD OVER THE NASHUA RIVER
|
| Location: |
|
| Resident Engineer: | Stephen Romano![]() |
| Construction Contract Value: | $5,845,665.00 |
| Construction Bid Price: | $5,291,786.75 |
| Initial Construction Estimate: | $4,344,530.50 |
| District: | District 3 |
| Current Status: | The contractor opened the roadway July 17th 2008 and completed all contract items. The contractor still has some minor punch-list work to complete. (as of 09/02/2008) |
|