Project Description:
HARVARD- SHIRLEY- BRIDGE REPLACEMENT, BR# H-09-025=S-13-018, HOSPITAL ROAD OVER THE NASHUA RIVER
Location:
  • Town of Harvard
  • Town of Shirley
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $5,845,665.00
    Construction Bid Price: $5,291,786.75
    Initial Construction Estimate: $4,344,530.50
    District: District 3
    Current Status: The contractor opened the roadway July 17th 2008 and completed all contract items. The contractor still has some minor punch-list work to complete. (as of 09/02/2008)

    Contracts (2) Progress
    # 44828 -- Construction Contract
    Harvard - Shirley - Bridge Replacement /Hospital Road over the Nashua River Completed
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/15/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor opened the roadway July 17th 2008 and completed all contract items. The contractor still has some minor punch-list work to complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/30/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Status Advertised 08/27/2005
    Project Management
    100% Design 100% Package Received 04/12/2005
    100% Design 100% Package Comments to DE 05/12/2005
    25% Design 25% Package Received 10/29/2002
    25% Design 25% Package Comments to DE 05/17/2003
    25% Design Design Public Hearing 11/13/2003
    75% Design 75% Package Received 10/01/2004
    75% Design 75% Package Comments to DE 01/05/2005
    Final Design PS&E Received 08/17/2005
    Final Design PS&E to FAPRO 08/17/2005
    Consultant Contract Process NTP Issued 07/15/2002