Project Description:
FALMOUTH- BRIDGE REHABILITATION, F-03-005, WATER STREET OVER EEL POND
The work under this project consists of a bascule (movable) bridge replacement which carries Water Street over Eel Pond Channel. The existing horizontal and vertical under clearances will remain unchanged. The work will mainly involve reconstruction of the bridge abutments, complete replacement of the moveable deck structure and all the machinery and electrical components, full depth roadway construction along the approaches to the bridge on Water Street, sidewalk reconstruction, and replacement of the bridge tender’s house. The bridge will be closed to vehicular traffic during construction and a detour route established around Eel Pond. A temporary pedestrian crossing will be provided for the duration of construction through the tourist off-season.
Location:
  • Town of Falmouth
  • Resident Engineer: Michael McGovern
    Construction Contract Value: $8,434,405.00
    Construction Bid Price: $7,634,550.00
    Initial Construction Estimate: $3,779,177.00
    District: District 5

    Contracts (3) Progress
    # 31241 -- Design -- Bridge Rehab/Recon/New Const
    Falmouth - Water St. over Eel Pond Moveable Bascule Bridge, BR# F-03-005 Final
    # 45509 -- Construction Contract
    Falmouth - Water Street over Eel Pond Channel (Bascule) Completed
    # 54827 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/14/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/18/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 08/20/2005
    Project Management
    100% Design 100% Package Received 05/20/2005
    100% Design 100% Package Comments to DE 07/08/2005
    25% Design 25% Package Received 08/27/2002
    25% Design 25% Package Comments to DE 11/29/2002
    25% Design Design Public Hearing 02/13/2003
    75% Design 75% Package Received 04/22/2004
    75% Design 75% Package Comments to DE 08/03/2004
    Final Design PS&E Received 07/18/2005
    Final Design PS&E to FAPRO 07/18/2005
    Consultant Contract Process NTP Issued 10/03/2001