| Project Description: |
WEST BOYLSTON- WORCESTER- LIGHTING IMPROVEMENTS ON ROUTE I-190 FROM EXIT 1 TO EXIT 4
Replacement of high mast lighting poles with median mounted poles.
|
| Location: |
|
| Resident Engineer: | James Gallagher![]() |
| Construction Contract Value: | $2,189,961.66 |
| Construction Bid Price: | $1,369,021.75 |
| Initial Construction Estimate: | $1,010,000.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||