Project Description:
WEST BOYLSTON- WORCESTER- LIGHTING IMPROVEMENTS ON ROUTE I-190 FROM EXIT 1 TO EXIT 4
Replacement of high mast lighting poles with median mounted poles.
Location:
  • Town of West Boylston
  • City of Worcester
  • Resident Engineer: James Gallagher
    Construction Contract Value: $2,189,961.66
    Construction Bid Price: $1,369,021.75
    Initial Construction Estimate: $1,010,000.00
    District: District 3

    Contracts (1) Progress
    # 34513 -- Construction Contract
    Lighting Improvements on a Section of Interstate 190. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/10/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/14/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 09/13/2003
    Project Management