Project Description:
MENDON- ROADWAY RECONSTRUCTION AT THE INTERSECTION OF PROVIDENCE STREET AND HARTFORD AVENUE
This project will result in the reconstruction of the intersection at Providence Street and Hartford Avenue, from 80-meters south to 90-meters north of the intersection on Providence Street, and extending easterly 150-meters on Hartford Avenue. Under this project, the intersection will be reconfigured to a “tee” type intersection to improve intersection geometrics for enhanced visibility, turning movements, and public safety. The work will include full depth reconstruction, widening of the roadway to include bicycle accommodations, traffic signs, pavement markings, utility relocations, drainage modifications, and landscaping.
Location:
  • Town of Mendon
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $437,750.00
    Construction Bid Price: $338,864.50
    Initial Construction Estimate: $313,830.00
    District: District 3
    Current Status: Project is completed. (as of 07/13/2006)

    Contracts (1) Progress
    # 35039 -- Construction Contract
    Roadway Reconstruction at the Intersection of Providence Street and Hartford Avenue. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/03/2004
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Project is completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/11/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 04/10/2003
    Project Status Advertised 10/11/2003
    Project Management
    25% Design 25% Package Received 06/24/2002
    25% Design 25% Package Comments to DE 10/22/2002
    25% Design Design Public Hearing 05/28/2003
    75% Design 75% Package Received 07/15/2003
    75% Design 75% Package Comments to DE 08/28/2003
    Final Design PS&E Received 10/07/2003
    Final Design PS&E to FAPRO 08/19/2003