HOPEDALE- MENDON- SIGNAL & INTERSECTION IMPROVEMENTS @ ROUTE 140 & HARTFORD AVENUE
The project will enhance safety and improve efficiency by installing a new traffic signal at the intersection of Route 140 and Hartford Avenue on the Hopedale-Mendon Town line. Hartford Avenue will be widened from its present 2 lanes to 4 lanes to reduce the existing delays at this intersection. This project will include the installation of crosswalks with wheelchair ramps and pushbutton pedestrian signals, as well as improved signs, drainage and pavement markings.
Location:
  • Town of Hopedale
  • Town of Mendon
  • Resident Engineer: Scott Fitzgerald
    Construction Contract Value: $2,014,694.53
    Construction Bid Price: $1,379,539.70
    Initial Construction Estimate: $1,150,120.00
    District: District 3

    Contracts (2) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 53687 -- Construction Contract
    Hopedale - Mendon - Intersection Reconstruction and Related Work at Route 140 (South Main Street/Cape Road) and Hartford Avenue Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/12/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/11/2000
    Project Review Committee PRC Approved 12/19/2000
    Project Review Committee Letter 01/04/2001
    Project Status Advertised 09/22/2007
    Project Management
    100% Design 100% Package Received 04/26/2007
    100% Design 100% Package Comments to DE 08/27/2007
    25% Design 25% Package Received 05/02/2005
    25% Design 25% Package Comments to DE 10/03/2005
    25% Design Design Public Hearing 02/28/2006
    75% Design 75% Package Received 08/04/2006
    75% Design 75% Package Comments to DE 11/03/2006
    Final Design PS&E Received 09/10/2007
    Final Design PS&E to FAPRO 09/11/2007