MARSHFIELD- NORWELL- BRIDGE REHABILITATION, M-07-001=N-24-001, UNION STREET/BRIDGE STREET OVER THE NORTH RIVER
This bridge project involves replacing the existing Union Street/Bridge Street over the North River superstructure with a new three span continuous steel superstructure. Replacement of this bridge involves reconstruction of approximately 380 feet of the north roadway approach, and 425 feet of the south roadway approach. Only one lane will remain open for two way vehicular traffic with a temporary signal during construction. The roadway reconstruction consists of minor realignment, drainage improvements, lighting, guardrail, and other miscellaneous improvements.
Location:
  • Town of Marshfield
  • Town of Norwell
  • Resident Engineer: Kevin Morrissey
    Construction Contract Value: $2,660,006.72
    Construction Bid Price: $2,279,919.00
    Initial Construction Estimate: $1,753,680.25
    District: District 5

    Contracts (1) Progress
    # 56972 -- Construction Contract
    Marshfield / Norwell - Bridge Reconstruction (M-07-001=N-24-001), Union Street / Bridge Street over the North River, PF #603360 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/31/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/21/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 07/19/2008
    Project Management
    100% Design 100% Package Received 02/16/2006
    100% Design 100% Package Comments to DE 05/03/2006
    25% Design 25% Package Received 10/31/2003
    25% Design 25% Package Comments to DE 03/04/2004
    75% Design 75% Package Received 02/10/2005
    75% Design 75% Package Comments to DE 11/28/2005
    Final Design PS&E Received 09/14/2007
    Final Design PS&E to FAPRO 09/20/2007
    Consultant Contract Process NTP Issued 01/02/2003