Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HAWLEY- BRIDGE REPLACEMENT, BR# H-13-006 PUDDING HOLLOW ROAD OVER CHICKLEY RIVER
The work consists of replacing the bridge over the Chickley River and realigning and changing the profile at Pudding Hollow Road so that the new bridge will be built on a new footprint located to the east of the existing structure.
Location:
  • Town of Hawley
  • Resident Engineer: Thomas Tierney
    Construction Contract Value: $1,065,536.00
    Construction Bid Price: $965,469.40
    Initial Construction Estimate: $959,582.00
    District: District 1
    Current Status: Bridge is open to traffic. Working on slope. (as of 09/26/2005)

    Contracts (2) Progress
    # 30281 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 34520 -- Construction Contract
    Bridge Replacement H-13-006 (Steel) - Pudding Hollow Road over the Chickley River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/30/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge is open to traffic. Working on slope.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/29/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 09/13/2003
    Project Management