Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BRIDGE REHABILITATION, B-16-029, ROUTE 99 (ALFORD STREET) OVER MYSTIC RIVER
The work under this project consists of rehabilitation of the structural, mechanical & electrical systems for the moveable span, replacement of the power and communication cables, new bridge signal equipment, pavement markings and signage, approach span structural repairs, approach roadway reconstruction and all incidental work.
Location:
  • City of Boston
  • Resident Engineer: Brian Cuddy
    Construction Contract Value: $54,490,031.00
    Construction Bid Price: $49,236,756.00
    Initial Construction Estimate: $24,493,000.00
    District: District 6

    Contracts (6) Progress
    # 54620 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection, and design and analysis of complex foundation rehabilitation projects. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60493 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects
    # 62665 -- Construction Contract
    Drawbridge Rehabilitation (B-16-029) (Steel) - Route 99 (Alford Street) over the Mystic River. Completed
    # 62937 -- Non-system contract type
    Statewide-Owner's Representative-Will perform peer reviews and manage cost recovery and value engineering for various projects.
    # 77865 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/06/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/20/2000
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 09/24/2005
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 06/08/2005
    100% Design 100% Package Received 02/02/2009
    100% Design 100% Package Received 05/27/2009
    100% Design 100% Package Comments to DE 08/13/2009
    25% Design 25% Package Received 07/13/2001
    25% Design 25% Package Comments to DE 06/02/2002
    75% Design 75% Package Received 02/18/2004
    75% Design 75% Package Comments to DE 04/20/2005
    Final Design PS&E Received 09/12/2005
    Final Design PS&E Received 09/17/2009
    Final Design PS&E to FAPRO 09/12/2005
    Final Design PS&E to FAPRO 09/17/2009