Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
ORANGE- RECONSTRUCTION OF NORTH MAIN STREET, FROM SCHOOL STREET TO LINCOLN AVENUE (0.4 MILES) INCLUDES RELOCATION OF FALL HILL BROOK CULVERT
The proposed project begins on North Main Street at the School Street intersection and ends at the intersection of Lincoln Avenue, a distance of approximately 0.4 miles. The project consists of roadway reconstruction, rehabilitation and reconstruction of various retaining walls and two major drainage culverts, construction of ADA accessible sidewalks and wheelchair ramps, drainage system modifications and improvements; construction of curb and bituminous concrete berm installations; traffic signing; landscaping and streetscape improvements and other incidental work.
Location:
  • Town of Orange
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Kimberley Sloan
    Estimated Total Contract Cost: $12,606,227.85
    Estimated Total Federal Participating Construction Cost: $13,849,525.12
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Franklin Regional Council of Governments.
    District: District 2
    Current Status: 100% Package Received (as of 11/15/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ORANGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2024, FFY 2025 and FFY 2026. MPO Project TEC Score 57/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,888,872.00
    State Cost: $1,222,218.00
    Total Cost: $6,111,090.00

    Planned Federal FY: 2025
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ORANGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2024, FFY 2025 and FFY 2026. MPO Project TEC Score 57/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,265,422.40
    State Cost: $816,355.60
    Total Cost: $4,081,778.00

    Planned Federal FY: 2026
    Responsible MPO: Franklin Regional Council of Governments
    Location: Municipality
    Cities: ORANGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Project is AC'd in FFY 2024, FFY 2025 and FFY 2026. MPO Project TEC Score 57/100.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $356,760.00
    State Cost: $89,190.00
    Total Cost: $445,950.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 12/15/2000
    Project Review Committee PRC Tabled 05/06/2002
    Project Review Committee PRC Approved 11/04/2002
    Project Review Committee Letter 11/04/2002
    Project Management
    100% Design 100% Package Received 11/15/2023
    25% Design 25% Package Received 02/26/2007
    25% Design 25% Package Received 07/16/2013
    25% Design 25% Package Comments to DE 08/29/2008
    25% Design 25% Package Comments to DE 10/02/2019
    25% Design Design Public Hearing 04/22/2009
    25% Design Design Public Hearing 04/07/2021
    75% Design 75% Package Received 11/08/2021
    75% Design 75% Package Comments to DE 11/24/2021