BELCHERTOWN- BRIDGE REPLACEMENT, B-05-005, RIVER STREET OVER JABISH BROOK
The proposed work includes the demolition of the existing bridge and the construction of a new bridge, as well as the reconstruction of the bridge approaches on River Street over the Jabish Brook. The new bridge will be built on the existing alignment and in the same location as the existing bridge. The proposed superstructure will consist of a 69 foot single span pre-stressed concrete butted box beams with a bituminous concrete riding surface. The proposed roadway width will carry two 12 foot travel lanes, a 1.3 foot right shoulder and a 6 foot sidewalk on the downstream side. The proposed work includes installation of new guard railings and pavement markings. The bridge will be closed during construction and traffic will be detoured
Location:
  • Town of Belchertown
  • Resident Engineer: James White
    Construction Contract Value: $1,482,204.85
    Construction Bid Price: $1,461,596.85
    Initial Construction Estimate: $1,383,745.82
    District: District 2
    Current Status: Bridge under construction (as of 04/10/2008)
    Additional Info: Bridge closed for duration of project. (as of 05/19/2008)

    Contracts (3) Progress
    # 32175 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract H Final
    # 52976 -- Construction Contract
    Belchertown - Bridge Replacement (B-05-005) - River Street over Jabish Brook Completed
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/26/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Bridge under construction
    Additional Info
    Bridge closed for duration of project.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/09/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 09/30/2006
    Project Management
    100% Design 100% Package Received 07/27/2006
    100% Design 100% Package Comments to DE 08/24/2006
    25% Design 25% Package Received 01/07/2005
    25% Design 25% Package Comments to DE 02/23/2005
    25% Design Design Public Hearing 03/31/2004
    75% Design 75% Package Received 10/12/2005
    75% Design 75% Package Comments to DE 04/05/2006
    Consultant Contract Process Scope to DE 09/18/2002
    Consultant Contract Process NTP Issued 02/28/2003