Project Description:
FREETOWN- BRIDGE PRESERVATION, BR# F-09-011, ROUTE 24 OVER ROUTE 79
The purpose of this project is to replace the bridge deck, while retaining the support beams and substructure. No changes will be made to the alignment of the bridge.
Location:
  • Town of Freetown
  • Resident Engineer: Gary Dixon
    Construction Contract Value: $3,701,860.00
    Construction Bid Price: $2,992,491.20
    Initial Construction Estimate: $2,435,657.60
    District: District 5

    Contracts (1) Progress
    # 45263 -- Construction Contract
    FREETOWN - Bridge Rehabilitation - F-09-011 - Rte 24 over Rte 79 (South Main Street) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/08/2006
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/16/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/26/2001
    Project Status Advertised 08/27/2005
    Project Status Advertised 10/29/2005
    Project Management
    100% Design 100% Package Received 06/30/2005
    Final Design PS&E Received 08/17/2005
    Final Design PS&E to FAPRO 08/17/2005