BRIDGEWATER- MIDDLEBOROUGH- BRIDGE REPLACEMENT, B-23-003=M-18-004, ROUTE 18 (BEDFORD STREET) OVER THE TAUNTON RIVER
The work under this project consists of replacing the Route 18 (Bedford Street) Bridge over the Taunton River. The new bridge will be a two span structure consisting of steel beams with a concrete deck and a sidewalk on the west side of the structure. The work will also include full depth roadway reconstruction along the approaches to the bridge. The bridge will be built in stages and one lane of traffic in each direction will be maintained throughout the duration of construction.
Location:
  • Town of Bridgewater
  • Town of Middleborough
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $5,216,196.52
    Construction Bid Price: $3,242,835.00
    Initial Construction Estimate: $3,146,813.00
    District: District 5

    Contracts (2) Progress
    # 30284 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 43702 -- Construction Contract
    Bridgewater/Middleborough - Route 18 over Taunton River B-23-003=M-18-004 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/02/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 05/07/2005
    Project Status Advertised 11/12/2005
    Project Management
    100% Design 100% Package Received 09/20/2004
    100% Design 100% Package Comments to DE 01/04/2005
    25% Design 25% Package Received 04/08/2002
    25% Design 25% Package Comments to DE 11/29/2002
    25% Design Design Public Hearing 02/26/2003
    75% Design 75% Package Received 12/04/2003
    75% Design 75% Package Comments to DE 08/12/2004
    Final Design PS&E Received 01/21/2005
    Final Design PS&E to FAPRO 04/06/2005
    Consultant Contract Process NTP Issued 12/04/2001