Project Description:
ATTLEBORO- BRIDGE RECONSTRUCTION, A-16-032, ROUTE 1A (NEWPORT AVENUE) OVER MBTA-AMTRAK-SHORE
The work under this project consists of the replacement of the Newport Avenue (Route 1A) Bridge over the MBTA/AMTRAK Railroad. The new structure will have a curb to curb width of approximately 72 feet, accommodating four 12-foot travel lanes and a 12-foot deceleration lane for the adjacent Bristol Plaza entrance. The proposed widening of the structure will help facilitate the staged construction requirements of maintaining 4 lanes of traffic during construction. The new structure will be a single span reinforced concrete deck supported on steel beams and new concrete abutments. The approach roadways to the bridge will be fully reconstructed approximately 300 to 400 feet on each side to match the existing grades of the roadway. The horizontal alignment will remain essentially the same. Cement concrete sidewalks will be constructed on both sides of the bridge.
Location:
  • City of Attleboro
  • Resident Engineer: Marc Cardinal
    Construction Contract Value: $10,127,796.00
    Construction Bid Price: $8,762,902.00
    Initial Construction Estimate: $10,290,415.00
    District: District 5

    Contracts (3) Progress
    # 30282 -- Design -- Footprint Bridge contracts
    Statewide Footprint Bridge Round 1 Final
    # 54336 -- Construction Contract
    Attlboro - Bridge Replacement (A-16-032) Route 1A over MBTA Completed
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/13/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 01/31/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 09/15/2007
    Project Management
    100% Design 100% Package Received 01/04/2007
    100% Design 100% Package Comments to DE 03/30/2007
    25% Design 25% Package Received 02/04/2003
    25% Design 25% Package Comments to DE 06/23/2003
    25% Design Design Public Hearing 03/30/2006
    75% Design 75% Package Received 07/21/2006
    75% Design 75% Package Comments to DE 12/11/2006
    Final Design PS&E Received 08/17/2007
    Final Design PS&E to FAPRO 09/11/2007
    Consultant Contract Process NTP Issued 12/04/2001