Project Description:
FALL RIVER- BRIDGE REHABILITATION, BR# F-02-021, CITY HALL PLAZA OVER I-195 EASTBOUND & WESTBOUND
The scope of work includes removal and replacement of the concrete stairs and ramps, portions of upper and lower concrete deck, installation of a new drainage system, installation of a new ceiling at the tunnel, fireproofing, and structural repairs. Other incidental work also includes, granite curb, cement concrete sidewalks, pedestrian lighting system, glass curtain wall with entrance doors, a new hydraulic elevator, tunnel standpipe system, pavement markings, streetscape amenities, and landscaping.
Location:
  • City of Fall River
  • Resident Engineer: Jeffrey Morra
    Construction Contract Value: $12,100,393.00
    Construction Bid Price: $14,279,069.00
    Initial Construction Estimate: $11,534,552.00
    District: District 5

    Contracts (1) Progress
    # 38586 -- Construction Contract
    Fall River - Bridge Rehabilitation (concrete) -City Hall Plaza over Route I-195 EB & WB Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/15/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/06/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/31/2001
    Project Status Advertised 12/20/2003
    Project Status Advertised 09/25/2004
    Project Management
    100% Design 100% Package Received 04/02/2004
    100% Design 100% Package Comments to DE 04/05/2004
    25% Design 25% Package Received 02/04/2003
    25% Design 25% Package Comments to DE 03/04/2003
    25% Design Design Public Hearing 11/07/2002
    75% Design 75% Package Received 06/06/2003
    75% Design 75% Package Comments to DE 12/03/2003
    Final Design PS&E Received 08/25/2004
    Final Design PS&E to FAPRO 12/18/2003