QUINCY- RECONSTRUCTION OF BURGIN PARKWAY AT CENTRE STREET, INCLUDES Q-01-049 & Q-01-051
This project involves three phases of construction which will alleviate traffic congestion at the intersection of Burgin Parkway and Centre Street. The first phase includes the construction of a new bridge to elevate the outbound Burgin Parkway traffic over the Centre Street intersection. This first phase also includes the construction of a new outbound ramp from the intersection of Congress Street and Crown Colony Drive to the existing northbound ramp to Route 3. Phase 2 will reconstruct the intersections at Burgin Parkway/ Centre Street and Crown Colony Drive/Congress Street. Phase 3 will construct an exclusive right turn from Centre Street onto the existing outbound ramps.
Location:
  • City of Quincy
  • Resident Engineer: Nicholas Delvento
    Construction Contract Value: $17,902,499.00
    Construction Bid Price: $15,862,172.00
    Initial Construction Estimate: $15,926,260.00
    District: District 4

    Contracts (1) Progress
    # 51399 -- Construction Contract
    Braintree - Quincy - Roadway Reconstruction and Related Work on Sections of Rte 3, Burgin Parkway and Center Street Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/05/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 02/20/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 11/26/2001
    Project Status Advertised 08/05/2006
    Project Management
    100% Design 100% Package Received 04/15/2005
    100% Design 100% Package Comments to DE 07/26/2005
    25% Design 25% Package Received 02/13/2003
    25% Design 25% Package Comments to DE 08/29/2003
    25% Design 25% Package Approved 09/20/2003
    25% Design Design Public Hearing 10/22/2003
    25% Design 25% Plans Complete 09/20/2003
    75% Design 75% Package Received 04/09/2004
    75% Design 75% Package Comments to DE 09/29/2004
    Final Design PS&E Received 10/07/2005
    Final Design PS&E to FAPRO 02/10/2006