Project Description:
AUBURN- BRIDGE REHABILITATIONS, BR#'S A-17-032 ROUTE I-290 EB & WB OVER SWORD ST. & A-17-030 ROUTE I-290 EB & WB OVER AUBURN ST.
The work to be done includes the removal of deteriorated concrete from the bridge and its replacement with new materials. Repairs will also be performed on the bridge bearings and the slopes under the bridge.
Location:
  • Town of Auburn
  • Resident Engineer: James Gallagher
    Construction Contract Value: $4,772,495.60
    Construction Bid Price: $3,420,466.00
    Initial Construction Estimate: $3,633,000.00
    District: District 3
    Current Status: All travel lanes have been re-opened. Spring 2005 work to consist of paving the top course and general project cleanup. (as of 09/07/2004)

    Contracts (1) Progress
    # 33134 -- Construction Contract
    Two Bridge Rehabilitation (A-17-30, A-17-32) - Interstate 290 over Auburn Street and Sword Street. (Alternate "B") Terminated

    Bridges

    Contract Dates
    Notice to Proceed: 12/19/2002
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All travel lanes have been re-opened. Spring 2005 work to consist of paving the top course and general project cleanup.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/14/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/29/2001
    Project Status Advertised 08/03/2002
    Project Management