| Project Description: |
ANDOVER- BRIDGE REPLACEMENT, BR# A-09-027, HIGH PLAIN ROAD OVER ROUTE I-93
The new bridge will be raised two feet higher over Interstate 93. The approach roadways will also be improved to accomodate the height of the new bridge to ensure safety.
|
| Location: |
|
| Resident Engineer: | Mark Fedele![]() |
| Construction Contract Value: | $4,720,156.98 |
| Construction Bid Price: | $3,850,689.50 |
| Initial Construction Estimate: | $2,590,144.00 |
| District: | District 4 |
| Current Status: | Final Inspection to be scheduled for late September 2008. (as of 09/12/2008) |
|