Project Description:
FRAMINGHAM- BRIDGE BETTERMENT, F-07-040, MAIN STREET OVER ROUTE 9
The work under this contract consists of jacking the superstructure to replace elastomeric bearings and installing bearing keeper plates; removing and patching repairing deteriorated areas of the diaphragms and concrete beams near the bearings; removing and patching repairing deteriorated areas of the concrete pier and abutments; repairing concrete cracks at the pier, abutments and diaphragms.
Location:
  • Town of Framingham
  • Resident Engineer: Scott Kallin
    Construction Contract Value: $736,403.60
    Construction Bid Price: $610,275.00
    Initial Construction Estimate: $662,605.50
    District: District 3

    Contracts (2) Progress
    # 30144 -- Design -- Bridge Rehab/Recon/New Const
    Statewide - Open End contract for Bridge Rehabilitation, Highway Operations Division. Final
    # 56846 -- Construction Contract
    Bridge Rehabilitation Br. No. F-07-040 (Concrete) Edgell Road/Main Street over Route 9 (Worcester Road) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/21/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/20/2001
    Project Review Committee PRC Approved 06/26/2001
    Project Review Committee Letter 10/29/2001
    Project Status Advertised 08/16/2008
    Project Management
    100% Design 100% Plans Complete 07/25/2008
    Final Design PS&E Received 06/30/2008
    Final Design PS&E to FAPRO 08/11/2008
    Consultant Contract Process Scope to DE 04/17/2006
    Consultant Contract Process NTP Issued 05/19/2006