Project Description: |
FRAMINGHAM- BRIDGE BETTERMENT, F-07-040, MAIN STREET OVER ROUTE 9
The work under this contract consists of jacking the superstructure to replace elastomeric bearings and installing bearing keeper plates; removing and patching repairing deteriorated areas of the diaphragms and concrete beams near the bearings; removing and patching repairing deteriorated areas of the concrete pier and abutments; repairing concrete cracks at the pier, abutments and diaphragms.
|
Location: |
|
Resident Engineer: | Scott Kallin |
Construction Contract Value: | $736,403.60 |
Construction Bid Price: | $610,275.00 |
Initial Construction Estimate: | $662,605.50 |
District: | District 3 |
|
Bridges
|
|
|
|
|